October 2026 Construction Update
Despite a wet October, good progress was made across the site, with the ground floor slabs poured for River Homes 1-9.
Read more
13/10/2026
September 2026 Construction Update
Throughout September, construction works continued to progress well with the ground floor concrete pour to the middle carpark now complete.
Read more
01/09/2026
August 2026 Construction Update
Throughout August, detailed excavation, formwork and slab pour were completed for the Beesley Street middle section of the ground floor carpark.
Read more
05/08/2026
July 2026 Construction Update
Throughout July, piling works were completed, followed by the demobilisation of the piling rig.
Read more
02/07/2026
June 2026 Construction Update
In June, Rivara continued to progress well, with the final piling works nearing completion and scheduled to finish at the end of the month.
Read more
08/06/2026
May 2026 Construction Update
In May, we hit an incredible milestone which saw the tower crane erected on site and the excavation phase is well underway.
Read more
14/05/2026
April 2026 Construction Update
In April, bulk earthworks progressed well across site, with works on track with the construction program.