Rivara construction update in West End, one step closer to bring the vision to life.

Traders In Purple is pleased to share the October construction update for Rivara, West End.

Despite a wet October, good progress was made across the site, with the ground floor slabs poured for River Homes 1-9. At the Filmer Street Terrace Homes, detailed excavation commenced and footings were poured, while the Beesley Street Terrace Homes progressed with slab pours completed and vertical construction underway. Detailed excavation was also completed at the Victoria Street Terrace Homes, followed by the pouring of footings.

Works to the Level 2 carpark continued, with formwork progressing and reinforcement and post-tensioning installed in preparation for the first concrete pour. Civil works also advanced, with the site’s water connection completed and stormwater discharge works underway along Beesley Street.

Looking ahead to the remainder of November, it is set to be another busy month, with the first Level 2 carpark concrete pour scheduled for completion. At the Beesley Street Tower, works will progress through detailed excavation, vertical construction and the ground floor slab pour. The Victoria Street lift core is also scheduled to be poured and jumped.

Further progress is anticipated across the Terrace Homes, with the Victoria Street Terrace Homes moving into ground floor slab pours and the commencement of vertical construction. For the River Homes 10-12 ground floor slabs are also scheduled to be poured.

We look forward to bringing you more updates next month as construction continues to progress.