Traders In Purple is pleased to share the latest construction update for Rivara, West End.

In April, bulk earthworks progressed well across site, with works on track with the construction program. Piling works are actively underway and detailed excavation activities also commenced in late April, marking the transition into the next phase of groundworks and setting the foundation for upcoming structural works.

Looking ahead to May, bulk earthworks and foundation piling will continue and detailed excavation will progress. In exciting news, installation of the crane base and crane tower is anticipated for mid May and will mark an exciting milestone in the construction journey.

We look forward to bringing you more updates next month as construction continues to progress.