Traders In Purple is pleased to share the September construction update for Rivara, West End.

Throughout September, construction works continued to progress well with the ground floor concrete pour to the middle carpark now complete.

Footings have been poured for the Terrace Homes along both Beesley Street and Victoria Street, while both apartment lift core bases have also been completed.

Ground level walls to the Beesley Street lift core have been poured, and another significant milestone was achieved with the completion of the first ground floor slab pour to the River Homes.

Looking ahead to the remainder of October, construction works are expected to focus on detailed excavation throughout the upper carpark area, alongside continued blockwork to the remaining River Home pool.

Structural works will also progress with the pouring of ground level walls to the Victoria Street lift core, while ground floor concrete pours are scheduled for the Terrace Homes along both Beesley Street and Victoria Street.

We look forward to bringing you more updates next month as construction continues to progress.